The Fastest Bay Area Cities for ADU Permits (2026 Data)
Among large Bay Area jurisdictions, Napa County (107 days) and Sunnyvale (133 days) had the fastest median ADU permit times in 2024, and San Francisco was the slowest at 332 days. The Bay Area median from application to permit was 182 days, up from 113 days in 2022, according to an analysis of state housing data.

How fast do Bay Area cities issue ADU permits?
Every California city follows the same state ADU law, but they don't move at the same speed. State law gives a city 60 days to approve or deny a complete ADU application. In practice, the clock pauses each time the city sends corrections back, and many projects go through two or three rounds.
The public numbers below come from cities' annual reports to the California Department of Housing and Community Development, matched permit by permit from application to issuance. Some cities, including Berkeley and the city of San Mateo, were left out of that analysis because of gaps in their reporting.
Median ADU permit time by jurisdiction, 2024
Jurisdiction | Median days, application to permit |
|---|---|
Napa County | 107 |
Sunnyvale | 133 |
San Jose | 161 |
Bay Area median | 182 |
Oakland | 230 |
Santa Clara (city) | 238 |
San Francisco | 332 |
What Type Five's own permits show
Across 15 Type Five projects first submitted between June 2025 and May 2026 that now have a building permit, the median time from first submittal to issued permit was 120 days. The fastest took 50 days and the slowest 196. Six of the 15 were issued within 90 days and eight within 120.
A few caveats. Fifteen permits is a small sample. It only counts projects that already have a permit, so slower projects still in review aren't in it yet, which makes the numbers look faster. And most cities below have just one or two of our permits, so each row is a single project's experience, not a city average.
Type Five ADU permit times by city
City | Days to permit (each value is one project) |
|---|---|
El Cerrito | 50, 74 |
Hillsborough | 59 |
Berkeley | 82, 195 |
Oakland | 82 |
Lafayette | 88, 129 |
San Mateo | 98 |
Kensington | 120 |
Walnut Creek | 142 |
Daly City | 158 |
Orinda | 176 |
Pleasanton | 196 |
All 15 permits | Median 120, range 50 to 196 |
Why the same ADU can take 50 days in one city and 200 in another
- Correction rounds. The 60-day clock stops whenever plans go back for changes. Fewer rounds is the biggest lever you have.
- Other departments. Fire, public works, sewer and urban forestry reviews can run in parallel or one after another, depending on the city.
- Site conditions. Hillsides, fire hazard zones, protected trees and sewer upgrades add reviewers and documents.
- Staffing and workload. A city can be fast one year and slow the next. The Bay Area median rose from 113 days in 2022 to 182 days in 2024.
How to get an ADU permit faster
- Check the city's rules before design starts. Setbacks, height, trees and parking rules differ a lot even between neighboring towns. Our city guides below summarize them.
- Submit a complete, coordinated set. Structural, energy and site plans that agree with each other draw fewer comments.
- Answer corrections quickly. Every week your plans sit with you is a week the permit isn't moving.
- Use a team that does it all. When the designer and builder are the same company, plan check answers don't wait on a handoff.
Some cities also offer pre-approved or permit-ready ADU plans. They can save design time on simple lots, but they don't remove site review. See our Los Altos page for one example.
After the permit: building the ADU
A permit is the midpoint, not the finish line. Type Five builds every ADU on site with conventional wood framing, and our build schedule page shows how construction is sequenced from foundation to final inspection.
Planning a budget too? Our Bay Area ADU cost guide breaks down design, permit fees, site work and construction.
What our clients say
Don’t just take our word for it. Read more in-depth client testimonials.
"The design process with Type Five felt more streamlined, and the experience allowed us to stay focused and avoid being overwhelmed by too many options."
“I feel like we got all the benefits of a custom build, without the uncertainty.”
"Type Five was really attractive because that's what they were offering: a full-service construction company with an established design system."
Want a realistic permit timeline for your lot?
Tell us your address and what you want to build. We'll tell you what your city requires, which reviews apply to your site and how long we'd expect permitting to take.
How our process works
One team takes your project from first sketch to move-in, with a fixed budget before construction starts.




FAQs about ADU permit times in the Bay Area
Short answers to common questions about how long ADU permits take.
How long does it take to get an ADU permit in the Bay Area?
The Bay Area median was 182 days from application to permit in 2024, up from 113 days in 2022, based on an analysis of state housing data. Times vary widely by city.
Which Bay Area city approves ADUs fastest?
Among the jurisdictions in that analysis, Napa County (107 days) and Sunnyvale (133 days) had the fastest 2024 medians. San Francisco was the slowest at 332 days.
Do cities have to approve an ADU within 60 days?
Yes, a city must approve or deny a complete ADU application within 60 days. The clock stops when the city returns the application for corrections, so total time is usually longer.
How long do Type Five's ADU permits take?
Across 15 Type Five projects first submitted between June 2025 and May 2026 that now have a building permit, the median time from first submittal to issued permit was 120 days. The fastest took 50 days and the slowest 196. Projects still in review aren't included.
Is an ADU faster to permit than a new house?
Generally, yes. The same analysis found a 2024 Bay Area median of 285 days for new single-family homes, compared with 182 days for ADUs.
Do pre-approved plans make permits faster?
They can shorten design and plan review on simple sites, but site plans, utilities and any tree, fire or hillside review still apply.
Why isn't Berkeley in the public data?
The public analysis left out Berkeley and the city of San Mateo because of gaps in their state reports. Type Five's two Berkeley permits in this sample took 82 and 195 days.